Skip to main content

Calaveras County Civil Grand Jury Review of Calaveras County Water District

Background

The 2023–2024 Calaveras County Civil Grand Jury (CCCGJ) conducted an investigation into the Calaveras County Water District (CCWD).

The focus areas included:

  • A five-year water and wastewater rate study
  • Vehicle lease program
  • ERP software integration
  • Workplace culture

The resulting report was titled “Still Waters Run Deep.”

2024 CCCGJ Report - Still Waters Run Deep.pdf

Initial Findings and Response

  • CCCGJ issued findings and recommendations.
  • CCWD responded in compliance with Penal Code §933(c) and §933.05, including a summary of implemented actions.
  • The 2024–2025 CCCGJ reviewed these responses and confirmed:
    • Legal compliance was met.
    • Public outreach aligned with Proposition 218 requirements.
    • Communication had improved, but further outreach enhancements were recommended.

Follow-Up Report: “The Cost of Water” (June 2025)

2025 CCCGJ Report - The Cost Of Water.pdf

This report provided updated commentary and recommendations on CCWD’s rate-setting and public engagement practices.

Key Findings

  • F1: CCWD responded timely and appropriately to the 2023–2024 report.
  • F2: CCWD met Proposition 218 requirements for public meetings and rate change communication.

Recommendations

  • R1: No further action required regarding the 2023–2024 findings.
  • R2: CCWD should continue evaluating and improving public outreach annually, with the first review by December 31, 2025.

CCWD's Response & Discussion to the CCCGJ Reports

2024.10.04 CCGJ District Response Letter.pdf2025.09.02 Final 2025 Grand Jury Reponse.pdf

 

July 24, 2024 Board Meeting

September 24, 2024 Board Meeting

August 27, 2025 Board Meeting

 

Join our mailing list