Activity is ramping up at Copper Cove. Mozingo Construction is preparing to begin mainline installation, with a small crew already mobilizing at Tank C with crews beginning with the potholing process, and full pipeline installation is scheduled to begin in late December.
Important Notice:
Changeable Message Signs will be placed along Little John Road to notify drivers of upcoming road closures.
Road Closure Schedule
- Dec 16 - Dec 24, 2025: From Kiva Pl. to Moccasin St.
Dates are subject to change due to weather and production.


Project Name: Copper Cove Booster Pump Station Modifications and Transmission Line CIP 11122
Project Location: Copperopolis, CA
Brief Description: The Project for the Calaveras County Water District is located in the community of Copperopolis, California.
The Project consists of the following work:
- Construction of approximately 12,000 LF of 20” ductile iron transmission main, connecting the Copper Cove Water Treatment Plant (WTP) booster pump station (BPS) (located at Kiva Place) to the C-Tanks.
- Installation of three (3) high-head pumps at the BPS.
- Installation of Electrical, Instrumentation, and Controls associated with the high-head pumps.